SB 256

  • California Senate Bill
  • 2025-2026 Regular Session
  • Introduced in Senate Feb 03, 2025
  • Passed Senate Jun 03, 2025
  • Assembly
  • Governor

Electricity: electrical infrastructure: wildfire mitigation.

Abstract

Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities are under the direction of their governing boards. Existing law requires electrical corporations, electrical cooperatives, and local publicly owned electric utilities to construct, maintain, and operate their electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire, as specified. Existing law requires electrical corporations to annually prepare and submit wildfire mitigation plans to the Office of Energy Infrastructure Safety for review and approval. Existing law also requires local publicly owned electric utilities and electrical cooperatives to annually prepare wildfire mitigation plans and submit the plans to the California Wildfire Safety Advisory Board, as specified. Existing law requires that each wildfire mitigation plan include, among other things, a description of the preventive strategies and programs to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, and a description of the appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines, as provided. This bill would require the commission, on or before January 1, 2027, to update a general order to require each electrical corporation to remove all permanently abandoned facilities, as specified. The bill would require an electrical corporation, for areas affected by wildfire that require electrical distribution infrastructure to be rebuilt, to consider the undergrounding of electrical distribution infrastructure if it is determined to be cost effective compared to other wildfire mitigation strategies. This bill would require an electrical corporation, for the description in the wildfire mitigation plan of the preventative strategies and programs to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, to include consideration of risks related to the wildland-urban interface. The bill would require an electrical corporation, for the description in the wildfire mitigation plan of the electrical corporation's appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines, to include consideration of enabling residents within a household who are not the customer of record to subscribe to receive notifications related to deenergization events and of communications with public safety partners, as provided. The bill would require that an electrical corporation's wildfire mitigation plan also include a description of the processes and procedures that the electrical corporation use to coordinate communications with local governments within the service area of the electric corporation, and include an accounting of all transmission facilities, including permanently abandoned facilities, and include a plan for how and when each permanently abandoned facility will be removed and the wildfire mitigation measures that are being implemented to prevent hazards, as provided. This bill would require local publicly owned electric utilities and electrical cooperatives, for the description in the wildfire mitigation plan of the preventative strategies and programs to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, to include consideration of risks related to the wildland-urban interface. The bill would require a local publicly owned electric utility or electrical cooperative's wildfire mitigation plan to include a description of the processes and procedures by which the local publicly owned electric utility or electrical cooperative coordinates communication with local governments within the service area of the local publicly owned electric utility or electrical cooperative, as specified. Existing law, the California Emergency Services Act, establishes, within the office of the Governor, the Office of Emergency Services (OES) under the supervision of the Director of Emergency Services. Existing law requires OES to establish a standardized emergency management system for use by all emergency response agencies. This bill would require certain electrical corporations and local publicly owned electric utilities, in cooperation with OES and other emergency service agencies, to establish procedures for the coordination of efforts between electrical corporations and local publicly owned electric utilities and their representatives and those of emergency response agencies. The bill would require these electrical corporations and local publicly owned electric utilities to assign liaison representatives to work within each local operations center, as provided. Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime. Because a violation of a commission action implementing certain of this bill's requirements would be a crime, the bill would impose a state-mandated local program. Additionally, by imposing new duties on local publicly owned electric utilities, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for specified reasons.

Bill Sponsors (3)

Votes


Actions


Aug 29, 2025

Assembly

August 29 hearing: Held in committee and under submission.

Aug 20, 2025

Assembly

August 20 set for first hearing. Placed on APPR. suspense file.

Jul 17, 2025

Assembly

Read second time and amended. Re-referred to Com. on APPR.

  • Amendment-Passage
  • Reading-1
  • Reading-2
  • Referral-Committee
Com. on APPR.

Jul 16, 2025

Assembly

From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 5. Noes 2.) (July 14).

Jul 10, 2025

Assembly

From committee with author's amendments. Read second time and amended. Re-referred to Com. on E.M.

  • Amendment-Passage
  • Committee-Passage
  • Reading-1
  • Reading-2
  • Referral-Committee
Com. on E.M.

Assembly

From committee: Do pass and re-refer to Com. on E.M. (Ayes 13. Noes 4.) (July 9). Re-referred to Com. on E.M.

  • Committee-Passage
  • Committee-Passage-Favorable
  • Referral-Committee
Com. on E.M.

Jun 25, 2025

Assembly

June 25 set for first hearing canceled at the request of author.

Jun 16, 2025

Assembly

From committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E.

  • Amendment-Passage
  • Committee-Passage
  • Reading-1
  • Reading-2
  • Referral-Committee
Com. on U. & E.

Jun 09, 2025

Assembly

Referred to Coms. on U. & E. and E.M.

  • Referral-Committee
Coms. on U. & E. and E.M.

Jun 04, 2025

Assembly

In Assembly. Read first time. Held at Desk.

Jun 03, 2025

Senate

Read third time. Passed. (Ayes 30. Noes 8. Page 1474.) Ordered to the Assembly.

May 23, 2025

Senate

Read second time. Ordered to third reading.

Senate

From committee: Do pass. (Ayes 5. Noes 1. Page 1193.) (May 23).

May 20, 2025

Senate

Set for hearing May 23.

May 19, 2025

Senate

May 19 hearing: Placed on APPR. suspense file.

May 09, 2025

Senate

Set for hearing May 19.

May 05, 2025

Senate

Read second time and amended. Re-referred to Com. on APPR.

  • Amendment-Passage
  • Reading-1
  • Reading-2
  • Referral-Committee
Com. on APPR.

May 01, 2025

Senate

From committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 2. Page 934.) (April 29).

Apr 11, 2025

Senate

Set for hearing April 29.

Apr 02, 2025

Senate

Re-referred to Com. on E., U & C.

  • Referral-Committee
Com. on E., U & C.

Mar 26, 2025

Senate

From committee with author's amendments. Read second time and amended. Re-referred to Com. on RLS.

  • Amendment-Passage
  • Committee-Passage
  • Reading-1
  • Reading-2
  • Referral-Committee
Com. on RLS.

Feb 14, 2025

Senate

Referred to Com. on RLS.

  • Referral-Committee
Com. on RLS.

Feb 04, 2025

Senate

From printer. May be acted upon on or after March 6.

Feb 03, 2025

Senate

Introduced. Read first time. To Com. on RLS. for assignment. To print.

Bill Text

Bill Text Versions Format
SB256 HTML
02/03/25 - Introduced PDF
03/26/25 - Amended Senate PDF
05/05/25 - Amended Senate PDF
06/16/25 - Amended Assembly PDF
07/10/25 - Amended Assembly PDF
07/17/25 - Amended Assembly PDF

Related Documents

Document Format
04/25/25- Senate Energy, Utilities and Communications PDF
05/16/25- Senate Appropriations PDF
05/25/25- Sen. Floor Analyses PDF
07/09/25- Assembly Committee on Utilities and Energy PDF
07/11/25- Assembly Emergency Management PDF
08/18/25- Assembly Appropriations PDF

Sources

Data on Open States is updated periodically throughout the day from the official website of the California State Legislature.

If you notice any inconsistencies with these official sources, feel free to file an issue.